Please find below note points before answering the question
Note:
- Material price control is V- Moving Average Price
- Project Stock (Respective WBS) is 0 at the time of Stock Transfer
- Above Stock Transfer is happening within same storage location or between two storage locations within a Plant
The correct Answer for this Question is Option 1 : Stock Account 100 Debit and Stock Account 100 Credit
This process is special and having accounting entries although the stock transfer is happened within same plant. Because the stock is moved from Normal Stock to Project Stock. In this case, Project Stock is 0 so the value of generated Project Stock is taken from Normal Stock price so we see the accounting entries as 100 which is equal to normal Stock. I hope it is clear. I will share one more question for the scenario where the Valuated Project Stock is available
FYI, No accounting entries are available for the transfer of normal stock within a same Plant (Valuation Area)
You can check my YouTube videos by searching as GANESH SAP in YouTube. Watch and Like my videos. SHARE with your circle.
Best Regards,
Ganesh
SAP WM-RF Course |
https://www.udemy.com/course/sap-wm-course-on-rfmobile-data-entry/?couponCode=6CDD261ADFB996ED4E36 |
SAP MM-WM Integration Course |
https://www.udemy.com/course/sap-mm-wm-integration-course-by-ganesh-padala/?couponCode=C95F31CE4703BC7179E8 |
SAP MM Import and RTP Procurement Process |
https://www.udemy.com/course/sap-mm-import-and-rtp-procurement-process/?couponCode=542B2E6CD14DC4B29A5D |
SAP MM Consignment and Pipeline Procurement |
https://www.udemy.com/course/sap-mm-consignment-and-pipeline-procurement/?couponCode=8A9632D1B78E7BC13856 |
SAP MM Subcontracting and SAP Batch Management Process |
https://www.udemy.com/course/sapmm-subcontracting/?couponCode=39105796ACD3D09BCF19 |
SAP MM Master Data Course |
https://www.udemy.com/course/sap-mm-master-data-course/?couponCode=E5F9BE9CA186781C6F8F |