Error: Requirements planning is not active in plant GP01. Message No. 61139
Solution: Although you have maintained all MRP configurations and master data with proper MRP Type, you are still getting this error during MRP Run. Then, you can check this configuration to fix the issue.
SPRO –> Materials Management –> Consumption-Based Planning –> Planning –> Activate Material Requirements Planning

Once you click on the note, you will get the screen below. You go to Material Requirement Planning button.

Now you choose the required Plant and click on the activate check box and save. System will create a Transport Request.

You can check the below link for complete SAP S/4 HANA MM Content
Thanks, and Best Regards,
Ganesh Padala