SAP ECC MRP Support Issue with Solution – SAP ECC only


Error: Requirements planning is not active in plant GP01. Message No. 61139

Reproducing the Issue: Run MRP for the Plant to reproduce the issue

Solution: Although you have maintained all MRP configurations and master data with proper MRP Type, you are still getting this error during MRP Run. Then, you can check this configuration to fix the issue.

SPRO –> Materials Management –> Consumption-Based Planning –> Planning –> Activate Material Requirements Planning

Learn well and share to help others.

Best Regards,

Ganesh Padala